Progress

Posted on Thu 05/28/09 in House quest

Still semi worn out from the work yesterday evening, I’m here posting an update on the progress.

First of all, lets break down the main activities of Things That Need To Be Done:

  1. Sand all walls
  2. Attach glue and glass fiber wallpaper to the walls
  3. Paint the walls
  4. Paint the ceilings in the attic
  5. Sand the stairs
  6. Paint the stairs 2-3 times
  7. Sand the window frames
  8. Paint the window frames
  9. Place kitchen (competent people will do this July 2nd)
  10. Place floor at ground level (competent people will do this July 6th)
  11. Place floor at upper levels

Basically it almost comes down to SandAndPaint(Everything);

My parents, friends and I have been busy with various things thus far. All walls have been sanded and wallpaper has been added to 95% of the second floor. The walls and ceiling near the attic stairs have been painted as well and all window frames have been sanded. Yesterday, I nearly completed the sanding of the attic stairs (can complete them when all work in the attic is done).

Today, my parents are going to get some painting done, so yay :-) Of all the work done, the wallpapering has been the most disappointing.. not the result, but the amount of time going into it; it’s enormous! I do have faith in completing everything before the kitchen will be placed in July. If I’m not too lazy, I’ll post another update for myself to read.